Location |
Samutsakhon |
Start |
April 2021 |
Finish |
September 2021 |
Contract |
Turn key THB 20.70 Million |
Load |
2,500 kVA |
Man-hours |
28,800 MH used 30 people at peak |
Safety incident |
LTls : ZERO MTls : ZERO |
Scope |
Design supply and installation for
|